Project Date
August 2026
Project Duration
3 Days (plant shutdown)
Client
Oji Fibre Solutions
Location
Tasman Mill

Project Description
During the recent Tasman Mill shutdown, MPF Engineering was tasked with replacing a critical 600NB process mill water line beneath the basement. With only a three-day shut window, restricted access, and two separate wall penetrations to work through, the project demanded precise pre-shut planning and a well-coordinated installation team. The job was delivered ahead of schedule.
Scope of Work:
- Pre-shut planning and sequencing to fit a three-day critical path window
- Fabrication of new 600NB stainless steel process water piping
- Removal of the existing carbon steel line from the basement area
- Installation of the new stainless line in a confined, limited-access space
- Tie-in through two separate wall penetrations
- Completion and handover ahead of the scheduled shut programme
Alongside this and a second critical path project, MPF Engineering also delivered additional projects across the site and supported the mill's maintenance team with emergent work throughout the shutdown. The result reflects what we bring to every shut: thorough planning, flexible resourcing, and a team that delivers on time.