CD 3 Isolation Upgrades

Home » Projects » CD3 Isolation Upgrades
CD 3 Isolation Upgrades - Project by MPF Engineering
CD 3 Isolation Upgrades - Project by MPF Engineering
CD 3 Isolation Upgrades - Project by MPF Engineering

Project Date

August 2023

Project Duration

11 Days + pre work

Client

Oji Fibre Solutions Tasman

Location

Kawerau

Oji Fibre Solutions

Project Description

MPF Engineering completed isolation upgrade works involving the supply, prefabrication, installation, and testing of process pipework.

The scope included workshop pre-spooling and on-site installation of Schedule 40 pipework, ranging from 50 NB to 250 NB. All welding was completed in accordance with approved ASME IX welding procedures, with 100% radiographic testing (RT) carried out on all welds to ensure full integrity and compliance.

Comprehensive inspection, testing, and documentation were provided as part of the project delivery.

 

Scope & Quality Assurance

  • Isolation upgrade works
  • Schedule 40 pipework ranging from 50 NB to 250 NB
  • Workshop pre-spooling and site installation
  • Welding completed to ASME IX procedures
  • 100% radiographic NDT on all welds
  • Pressure testing completed
  • Full Inspection and Test Plans (ITP) and NDT records supplied