Project Date
September 2023
Project Duration
1 Month
Client
Oji Fibre Solutions Tasman
Location
Kawerau

Project Description
MPF Engineering completed a hypochlorine dosing system upgrade involving site measurement, workshop prefabrication, and staged installation.
The scope of work included detailed site measurement of existing pipework, prefabrication of new headers in MPF Engineering’s workshop, and the removal of redundant piping. Installation was carried out over a 10-day programme to align with site operational requirements.
Standards & Quality Assurance
- Site measurement and workshop prefabrication of pipework headers
- Removal of old and redundant piping
- Installation completed over a 10-day period
- Stainless steel support brackets supplied and installed
- Pipework ranging from 50 NB to 250 NB
- Schedule 40 PVC pressure pipe
- Workshop pre-spooling and site installation
- Pressure testing completed
- Full Inspection and Test Plans (ITP) and NDT records provided