Project Date
August 2022
Project Duration
2 Months
Client
Coollogic Auckland
Location
Motueka

Project Description
MPF Engineering was contracted to carry out the installation of process piping for new ice cream churns at the Motueka Creamery.
The scope of work included ammonia and glycol piping systems associated with refrigeration plant upgrades. Installation was completed in accordance with ASME IX welding procedures and ASME B31.3 piping code requirements, ensuring compliance and reliable system performance.
Standards & Quality Assurance
- Installation of piping for new ice cream churns
- 280 mm Mycom compressor integration
- Ammonia pipework
- Stainless steel glycol tubing
- Welding and piping completed to ASME IX / ASME B31.3