Project Date
April 2023
Project Duration
12 Months
Client
ABC Pipe Fitters/Aquaheat
Location
Tauriko, Tauranga
Project Description
MPF Engineering completed the installation of carbon steel pipework to supply natural gas throughout the Winstone Wallboards GIB board manufacturing facility.
The scope of work included the supply, prefabrication, and installation of natural gas pipework, with pre-spooling carried out in MPF Engineering’s workshop to improve quality control and site efficiency. All works were completed in accordance with applicable gas and piping standards.
Standards & Quality Assurance
- Natural gas pipework installation
- Carbon steel pipework ranging from 50 NB to 250 NB
- Schedule 40 pipe
- Pipework installed to ASME B31.8 requirements
- Workshop pre-spooling completed by MPF Engineering
- Pressure testing carried out
- Full Inspection and Test Plans (ITP) and NDT records provided