Project Date
October 2022
Project Duration
6 Months
Client
Lawter
Location
Lawter Site

Project Description
This project involved pipework upgrades associated with the R101 system and fuel supply infrastructure within an operational factory environment.
The scope of work included the removal of redundant pipework and the installation of new Schedule 10 stainless steel replacement lines. Works were carefully planned and executed around live factory operations and scheduled shutdown periods to minimise disruption to production.
MPF Engineering provided full Issued for Construction (IFC) isometric drawings and carried out design verification of the pipework to ensure compliance with project and operational requirements.
Standards & Quality Assurance
- Removal of old and redundant pipework
- Installation of Schedule 10 stainless steel replacement lines
- Brownfields work within an operational factory
- Works coordinated around planned shutdowns
- IFC construction isometric drawings provided
- Pipework design verification completed