Rosedale WWTP | Bio-Gas Pipework

Home » Projects » Rosedale WWTP | Bio-Gas Pipework
Rosedale WWTP | Bio-Gas Pipe Work - Project by MPF Engineering
Rosedale WWTP | Bio-Gas Pipe Work - Project by MPF Engineering
Rosedale WWTP | Bio-Gas Pipe Work - Project by MPF Engineering

Project Date

June 2022

Project Duration

6 Months - intermittent delivery times due to site

Client

Fulton Hogan Ltd.

Location

Rosedale, Auckland

Fulton Hogan

Project Description

MPF Engineering assisted Fulton Hogan at the Rosedale Wastewater Treatment Plant (WWTP) with the prefabrication and installation of biogas pipework.

The scope of work included pipe pre-spooling and on-site fitting of 300 NB pipework, carried out in accordance with project specifications and quality requirements. All works were supported by comprehensive quality assurance and inspection processes.

Standards & Quality Assurance

  • Pipe pre-spooling and installation of 300 NB biogas pipework
  • IFC (Issued for Construction) isometric drawings supplied
  • Full QA pack including Inspection and Test Plan (ITP)
  • Radiographic Non-Destructive Testing (NDT) completed at 10%
  • In-house hydrostatic testing carried out