Project Date
June 2022
Project Duration
6 Months - intermittent delivery times due to site
Client
Fulton Hogan Ltd.
Location
Rosedale, Auckland

Project Description
MPF Engineering assisted Fulton Hogan at the Rosedale Wastewater Treatment Plant (WWTP) with the prefabrication and installation of biogas pipework.
The scope of work included pipe pre-spooling and on-site fitting of 300 NB pipework, carried out in accordance with project specifications and quality requirements. All works were supported by comprehensive quality assurance and inspection processes.
Standards & Quality Assurance
- Pipe pre-spooling and installation of 300 NB biogas pipework
- IFC (Issued for Construction) isometric drawings supplied
- Full QA pack including Inspection and Test Plan (ITP)
- Radiographic Non-Destructive Testing (NDT) completed at 10%
- In-house hydrostatic testing carried out