Secondary SBLOX Tank Refurbishment

Home » Projects » Secondary SBLOX Tank Refurbishment
Secondary SBLOX Tank Refurbishment: Oji Tasman Mill, Kawerau
Secondary SBLOX Tank Refurbishment: Oji Tasman Mill, Kawerau

Project Date

August 2026

Project Duration

8 Days (plant shutdown)

Client

Oji Fibre Solutions

Location

Tasman Mill, Kawerau

Oji Fibre Solutions

Project Description

MPF Engineering completed a major refurbishment of the 8 m diameter Secondary SBLOX Tank in the Steam & Recovery area at Oji Fibre Solutions' Tasman Mill in Kawerau. The work was done during an 8-day critical-path plant shutdown. It covered annular floor replacement, a new flush drain manway, partial outer strake replacement, and replacement of the duplex 2205 inner upper strake, all to API 650 and API 653. Our team worked day and night shifts around the clock and handed the tank back one day ahead of schedule.

Scope of Work:

  • Temporary support of approximately 25 tonnes of tank weight while the existing annular floor plates were removed
  • Installation of new annular floor plates on the 8 m diameter tank
  • Workshop fabrication of the flush drain manway insert
  • Furnace post weld heat treatment of the manway insert before site installation, to meet API 650/653 requirements
  • Site installation of the flush drain manway and partial outer strake replacement
  • Duplex 2205 inner upper strake replacement, run at the same time as the annular floor and manway works
  • Continuous 24/7 day and night shifts across the 8-day shutdown

With around 25 tonnes of tank weight carried on temporary supports, the floor replacement needed careful engineering and close control on site. Three things let us finish inside a tight 8-day window: planning, workshop prefabrication, and running several work fronts at once. The project reflects MPF Engineering's ongoing support of Oji's Steam & Recovery operations. It also shows we can deliver complex, code-compliant tank repairs safely under shutdown pressure.