Project Date
May 2021
Project Duration
4 Months
Client
Dobsons Refridgeration
Location
Opotiki
Project Description
MPF Engineering was contracted to carry out the installation of process piping for the Whakatohea Mussel Processing Factory.
The scope of work included the installation of Schedule 40, 304-grade stainless steel pipework, manufactured and installed in accordance with ASME IX and ASME B31.3 standards. The piping system formed part of a CO₂ refrigeration system designed and rated for operating pressures up to 52 bar.
Standards & Specifications
-
ASME IX / ASME B31.3 compliant
-
Schedule 40, 304 stainless steel
-
CO₂ system rated to 52 bar