Geothermal Steam Upgrade

Geothermal Steam Upgrade

Home Geothermal Steam Upgrade
  • Project Date

    09.09.2023

  • Project Duration

    Pre Fabrication 1 Month – Install Annule Shut 11 day window

  • Client

    Oji Fibre Solutions Tasman

  • Location

    Kawerau

Project Description

Assist Oji with design of system. Schedule tie in times and location.

  • ASME B31.1
  • 25nb to 300nb sch40 pipe
  • Supply and install with workshop pre-spooling
  • 3rd party witnessed hydro test
  • ITP and NDT records
  • 100% RT on all site welds