Project Date
30.09.2023
-
Project Duration
1 month
-
Client
Oji Fibre Solutions Tasman
-
Location
Kawerau
Project Description
Site measure of pipe work and pre fabricate headers in workshop. Destruct of old redundant piping. Install over 10 days.
- Stainless steel brackets
- 50nb to 250nb sch40 PVC P
- Supply and install with workshop pre-spooling
- Pressure Test
- ITP and NDT records