Project Date
April 2023
-
Project Duration
12 Months
-
Client
ABC Pipe Fitters / Aquaheat
-
Location
Tauranga, Tauriko
Project Description
Install of carbon pipework to supply natural gas throughout the Winstone wallboards GIB board facility.
- ASME B31.8
- 50nb to 250nb sch40 pipe
- Supply and install with workshop pre-spooling
- Pressure test
- ITP and NDT records